Name and Location
of Project
Client
Value
($ 000 000)
Date
Project Details
Goethals Bridge
NEW YORK
The Port
Authority of
NY&NJ
62.0
2003 - 07
.
.
Rehabilitation of deck, structural steel and
replacement of sidewalks
3rd Ave. Bridge on East River
NEW YORK
NYC
DoT
119.5
2002 - 05
2 000
t New steel swing bridge
(inc. Elect. and Mech. works)
Demolishing existing bridge
New foundations and approach ramps
Marine Parkway Lift Bridge
NEW YORK
MTA
96.0
1998 - 02
3 000
lf Concrete pre-cast deck installation
Replacement of major structural
steel elements
Housing Complex (Wildflower Estates)
New YORK
WFD
26.1
1998 - 02
57
ea 3 - 4 Story town house complex
Newtown Creek - NC - 26 G
Water Pollution Control Plant
NEW YORK
DEP
59.8
1995 - 00
.
. Upgrading of sewage treatment plant,
pump station and mechanical systems
Greenbelt Route Park Road Tunnels
WASHINGTON DC
(40% of Kajima - Kiska JV)
WMATA
105.0
1994 - 98
2 x 3 200
lf Twin tunnels (16'8" dia.) in soft ground
9" Precast segment initial lining
16" Final lining
Greenbelt Route 14th St Tunnels
WASHINGTON DC
(60% of Kiska - Kajima JV)
WMATA
65.0
1994 - 97
2 x 3 200
lf Twin tunnels (16'8" dia.) in soft ground
9" Precast segment initial lining
16" Final lining
Shafts 21B - 22B for Tunnel 3 Stage 2
NEW YORK
NY-DEP
48.8
1992 - 94
199
.
178
m
.
m
Shaft 21B : 12 - 7 m diameter
(soft ground freezing)
Shaft 22B : 12 - 4 m diameter
(soft ground freezing)
CPW 353 Luxury Residences
NEW YORK
KDI Inc.
22.5
1992 - 93
.
. 22 - Story luxury residences
18 Units - 60 000 sqft construction
Viaducts and Elevated Structures
NEW YORK
NYS DoT
77.0
1993 - 96
.
. Repair of structural steel, deck replacement,
abatement, electrical works, painting,
Rehabilitation of Bridges
NEW YORK
NYS DoT
NYC DoT
TBTA
MTA
195.3
1991 - 02
14
ea Rehabilitation and enlargement of bridges
Repair of structural steel, deck replacement,
bearing replacement,
stripping of lead paint, repainting
The Huntington Luxury Condominium
NEW YORK
1828 -
2nd Ave Ass
28.9
1989 - 91
. . 32 - Story residential condominium
108 Units - 130 000 sqft construction
816.9